Delivery recovery

Recovering delivery across two insurance platforms

Workstreams forecast to overrun by two and eight months delivered revised MVPs to production by their original planned launch dates.

A US small-business premises and UK terraced homes on a shared blue foundation, representing two insurance markets using one platform.

The challenge

A multinational insurance business was developing a reusable digital insurance interface across US small-business insurance and UK landlord insurance. Both workstreams were forecast to miss their planned launch dates: by approximately two months in the US and eight months in the UK. Scope creep, concentrated expertise, and limited cross-team collaboration were making recovery harder. The platform combined micro-frontends, event-driven services, machine-learning-supported risk propensity, and secure transaction processing in a regulated insurance environment. Recovery needed to address the delivery organisation as well as the planned functionality.

US business and cyber insurance and UK landlord insurance share a platform, with reduced initial release scope reaching planned launch points and other features deferred.

The work

I reviewed the existing Monte Carlo delivery forecasts and incorporated inputs informed by observed team behaviours and delivery patterns. I used that work to examine the practical risks behind the schedule, including expanding scope and knowledge held by too few people. I worked with Product Managers to agree smaller minimum viable products and revise priorities around release-critical capability. The recovery plan therefore changed what needed to be delivered for the first release, with the scope decisions made jointly across Product and Engineering. I coordinated execution with the Engineering Managers and encouraged team exchanges, wider communication, and knowledge sharing. These measures addressed the silos that constrained delivery and helped the teams focus on the agreed release priorities.

The result

Both the US and UK workstreams released their revised MVPs to production by the original planned launch dates. The releases served different markets—US small-business insurance and UK landlord insurance—using the same underlying platform. Product and Engineering had agreed which capabilities were essential for those first releases. That smaller scope provided the initial production capability needed for go-to-market readiness, with the broader feature set kept outside the launch commitment. The recovery therefore delivered working releases against the original schedule, with an explicit decision about what each release would contain.

Illustration of a working desk set up to coordinate two software releases.

Impact

The business preserved its planned route to market in two countries. Engineering capacity and product priorities were brought into the same decision, allowing the teams to focus on a first release they could deliver. The forecasts also became a basis for practical management decisions: what to prioritise, where expertise was concentrated, and how teams needed to work together. Scope agreement, team exchanges, and knowledge sharing connected the recovery plan to day-to-day delivery. The outcome depended on coordinated decisions across Product and Engineering, as well as the software itself.